Sale Value
₹47,899,142
Budget Value
₹32,573,266
Mat
₹26,640,467
Sub
₹116,526
FW
₹0
P&M
₹3,668,330
PRW
₹2,147,944
Variance
₹0
Activity Name
CS.4.3.C - M30 RCC
BOQ Quantity
5,966.51 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M30 GRADE | 5,966.51 | 1.000 | 4,465.00 | 4,465.00 | 26,640,467.15 | |
| PRW | L/c for pouring of RCC Concrete | 5,966.51 | 1.000 | 345.00 | 345.00 | 2,058,445.95 | |
| PRW | L/c Curing of concrete | 5,966.51 | 1.000 | 10.00 | 10.00 | 59,665.10 | |
| PRW | L/C for Hacking | 5,966.51 | 10.000 | 0.50 | 5.00 | 29,832.55 | |
| Sub | S/c Testing charges | 5,966.51 | 1.000 | 10.00 | 10.00 | 59,665.10 | |
| Sub | S/c Curing & other Miscellaneous Works | 5,966.51 | 0.953 | 10.00 | 9.53 | 56,860.84 | |
| P&M | Pumping & Lifting Charges | 5,966.51 | 1.000 | 614.82 | 614.82 | 3,668,329.68 | |
| 5,966.51 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹5,459.35 | ₹32,573,266.37 | |||||