Item Analysis

Sale Value

₹5,113,290

Budget Value

₹4,001,600

Mat

₹2,509,200

Sub

₹984,000

FW

₹0

P&M

₹180,400

PRW

₹328,000

Variance

₹0

Activity Name

CS.17.2.B - Struct. Steel

BOQ Quantity

32.80 MT

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat STRUCTURAL STEEL 32.80 1.050 70,000.00 73,500.00 2,410,800.00
Sub S/c Fabrication of structural steel works 32.80 1.082 24,500.00 26,499.20 869,173.76
PRW L/c Erection of Purlin Structures 32.80 1.000 10,000.00 10,000.00 328,000.00
Mat BOLT & NUT & WASHER-HSFG-24 X 130 MM 32.80 1.000 3,000.00 3,000.00 98,400.00
Sub S/c Refab STR steel incl 2coats red oxide primer&epoxy paint 32.80 1,000.228 3.50 3,500.80 114,826.17
P&M Lifting Charges 32.80 1.000 5,500.00 5,500.00 180,400.00
32.80 0.000 0.00 0.00 0.00
Selected Item Totals: ₹122,000.00 ₹4,001,599.93