Item Analysis

Sale Value

₹134,040,155

Budget Value

₹104,898,501

Mat

₹85,549,771

Sub

₹451,251

FW

₹0

P&M

₹1,798,166

PRW

₹17,099,312

Variance

₹1

Activity Name

CS.16.1.6 - Reinf. Steel

BOQ Quantity

1,419.03 MT

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat REINFORCEMENT STEEL-HYSD BARS-FE 500D 1,419.03 1.035 57,500.00 59,512.50 84,450,022.88
Mat WIRE-BINDING WIRE-GI 1,419.03 9.000 75.00 675.00 957,845.25
Mat PRECAST RCC/PSC ITEMS-COVER BLOCK 1,419.03 1.000 100.00 100.00 141,903.00
Sub S/C Hire charges for Automatic Rebar Cutting & Bending Plant 1,419.03 1.015 313.30 318.00 451,250.83
PRW L/c Reinforcement - Substructure 1,419.03 1.000 6,050.00 6,050.00 8,585,131.50
PRW L/c Steel Loading, unlaoding & shifting from yard to site 1,419.03 1.000 200.00 200.00 283,806.00
PRW L/c Lifting charge Reinforcement Steel-4F 1,419.03 29.000 200.00 5,800.00 8,230,374.00
P&M Lifting Charges 1,419.03 1.000 1,267.18 1,267.18 1,798,166.44
1,419.03 0.000 0.00 0.00 0.00
Selected Item Totals: ₹73,922.68 ₹104,898,499.89