Sale Value
₹104,934,933
Budget Value
₹82,121,054
Mat
₹70,004,036
Sub
₹369,251
FW
₹0
P&M
₹1,471,411
PRW
₹10,276,355
Variance
₹1
Activity Name
CS.16.1.3 - Reinf. Steel
BOQ Quantity
1,161.17 MT
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | REINFORCEMENT STEEL-HYSD BARS-FE 500D | 1,161.17 | 1.035 | 57,500.00 | 59,512.50 | 69,104,129.63 | |
| Mat | WIRE-BINDING WIRE-GI | 1,161.17 | 9.000 | 75.00 | 675.00 | 783,789.75 | |
| Mat | PRECAST RCC/PSC ITEMS-COVER BLOCK | 1,161.17 | 1.000 | 100.00 | 100.00 | 116,117.00 | |
| Sub | S/C Hire charges for Automatic Rebar Cutting & Bending Plant | 1,161.17 | 1.015 | 313.30 | 318.00 | 369,251.48 | |
| PRW | L/c Reinforcement - Substructure | 1,161.17 | 1.000 | 6,050.00 | 6,050.00 | 7,025,078.50 | |
| PRW | L/c Steel Loading, unlaoding & shifting from yard to site | 1,161.17 | 1.000 | 200.00 | 200.00 | 232,234.00 | |
| PRW | L/c Lifting charge Reinforcement Steel-4F | 1,161.17 | 13.000 | 200.00 | 2,600.00 | 3,019,042.00 | |
| P&M | Lifting Charges | 1,161.17 | 1.000 | 1,267.18 | 1,267.18 | 1,471,411.40 | |
| 1,161.17 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹70,722.68 | ₹82,121,053.76 | |||||