Sale Value
₹109,583,160
Budget Value
₹85,758,896
Mat
₹74,153,625
Sub
₹391,139
FW
₹0
P&M
₹1,558,631
PRW
₹9,655,500
Variance
₹1
Activity Name
CS.16.1.2 - Reinf. Steel
BOQ Quantity
1,230.00 MT
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | REINFORCEMENT STEEL-HYSD BARS-FE 500D | 1,230.00 | 1.035 | 57,500.00 | 59,512.50 | 73,200,375.00 | |
| Mat | WIRE-BINDING WIRE-GI | 1,230.00 | 9.000 | 75.00 | 675.00 | 830,250.00 | |
| Mat | PRECAST RCC/PSC ITEMS-COVER BLOCK | 1,230.00 | 1.000 | 100.00 | 100.00 | 123,000.00 | |
| Sub | S/C Hire charges for Automatic Rebar Cutting & Bending Plant | 1,230.00 | 1.015 | 313.30 | 318.00 | 391,139.39 | |
| PRW | L/c Reinforcement - Substructure | 1,230.00 | 1.000 | 6,050.00 | 6,050.00 | 7,441,500.00 | |
| PRW | L/c Steel Loading, unlaoding & shifting from yard to site | 1,230.00 | 1.000 | 200.00 | 200.00 | 246,000.00 | |
| PRW | L/c Lifting charge Reinforcement Steel-4F | 1,230.00 | 8.000 | 200.00 | 1,600.00 | 1,968,000.00 | |
| P&M | Lifting Charges | 1,230.00 | 1.000 | 1,267.18 | 1,267.18 | 1,558,631.40 | |
| 1,230.00 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹69,722.68 | ₹85,758,895.79 | |||||