Item Analysis

Sale Value

₹109,583,160

Budget Value

₹85,758,896

Mat

₹74,153,625

Sub

₹391,139

FW

₹0

P&M

₹1,558,631

PRW

₹9,655,500

Variance

₹1

Activity Name

CS.16.1.2 - Reinf. Steel

BOQ Quantity

1,230.00 MT

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat REINFORCEMENT STEEL-HYSD BARS-FE 500D 1,230.00 1.035 57,500.00 59,512.50 73,200,375.00
Mat WIRE-BINDING WIRE-GI 1,230.00 9.000 75.00 675.00 830,250.00
Mat PRECAST RCC/PSC ITEMS-COVER BLOCK 1,230.00 1.000 100.00 100.00 123,000.00
Sub S/C Hire charges for Automatic Rebar Cutting & Bending Plant 1,230.00 1.015 313.30 318.00 391,139.39
PRW L/c Reinforcement - Substructure 1,230.00 1.000 6,050.00 6,050.00 7,441,500.00
PRW L/c Steel Loading, unlaoding & shifting from yard to site 1,230.00 1.000 200.00 200.00 246,000.00
PRW L/c Lifting charge Reinforcement Steel-4F 1,230.00 8.000 200.00 1,600.00 1,968,000.00
P&M Lifting Charges 1,230.00 1.000 1,267.18 1,267.18 1,558,631.40
1,230.00 0.000 0.00 0.00 0.00
Selected Item Totals: ₹69,722.68 ₹85,758,895.79