Item Analysis

Sale Value

₹159,114,577

Budget Value

₹124,522,060

Mat

₹109,237,936

Sub

₹576,199

FW

₹0

P&M

₹2,296,067

PRW

₹12,411,858

Variance

₹1

Activity Name

CS.16.1.1 - Reinf. Steel

BOQ Quantity

1,811.95 MT

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat REINFORCEMENT STEEL-HYSD BARS-FE 500D 1,811.95 1.035 57,500.00 59,512.50 107,833,674.38
Mat WIRE-BINDING WIRE-GI 1,811.95 9.000 75.00 675.00 1,223,066.25
Mat PRECAST RCC/PSC ITEMS-COVER BLOCK 1,811.95 1.000 100.00 100.00 181,195.00
Sub S/C Hire charges for Automatic Rebar Cutting & Bending Plant 1,811.95 1.015 313.30 318.00 576,199.19
PRW L/c Reinforcement - Substructure 1,811.95 1.000 6,050.00 6,050.00 10,962,297.50
PRW L/c Steel Loading, unlaoding & shifting from yard to site 1,811.95 1.000 200.00 200.00 362,390.00
PRW L/c Lifting charge Reinforcement Steel-4F 1,811.95 3.000 200.00 600.00 1,087,170.00
P&M Lifting Charges 1,811.95 1.000 1,267.18 1,267.18 2,296,066.80
1,811.95 0.000 0.00 0.00 0.00
Selected Item Totals: ₹68,722.68 ₹124,522,059.12