Sale Value
₹47,517,386
Budget Value
₹32,313,353
Mat
₹25,258,411
Sub
₹95,389
FW
₹0
P&M
₹2,941,170
PRW
₹4,018,384
Variance
₹0
Activity Name
CS.13.6.D - M40 RCC
BOQ Quantity
4,783.79 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M40 GRADE (INTERNAL) | 4,783.79 | 1.000 | 5,280.00 | 5,280.00 | 25,258,411.20 | |
| PRW | L/c for pouring of RCC Concrete | 4,783.79 | 1.000 | 345.00 | 345.00 | 1,650,407.55 | |
| PRW | L/c Curing of concrete | 4,783.79 | 1.000 | 10.00 | 10.00 | 47,837.90 | |
| PRW | L/C for Hacking | 4,783.79 | 10.000 | 0.50 | 5.00 | 23,918.95 | |
| Sub | S/c Testing charges | 4,783.79 | 1.000 | 10.00 | 10.00 | 47,837.90 | |
| Sub | S/c Curing & other Miscellaneous Works | 4,783.79 | 0.994 | 10.00 | 9.94 | 47,550.87 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 4,783.79 | 32.000 | 15.00 | 480.00 | 2,296,219.20 | |
| P&M | Pumping & Lifting Charges | 4,783.79 | 1.000 | 614.82 | 614.82 | 2,941,169.77 | |
| 4,783.79 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹6,754.76 | ₹32,313,353.34 | |||||