Budget Value
₹30,998,141
Mat
₹24,828,237
Sub
₹90,882
FW
₹0
P&M
₹2,768,891
PRW
₹3,310,131
Variance
₹0
Activity Name
CS.13.5.C - M45 RCC
BOQ Quantity
4,503.58 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M45 GRADE (INTERNAL) | 4,503.58 | 1.000 | 5,513.00 | 5,513.00 | 24,828,236.54 | |
| PRW | L/c for pouring of RCC Concrete | 4,503.58 | 1.000 | 345.00 | 345.00 | 1,553,735.10 | |
| PRW | L/c Curing of concrete | 4,503.58 | 1.000 | 10.00 | 10.00 | 45,035.80 | |
| PRW | L/C for Hacking | 4,503.58 | 10.000 | 0.50 | 5.00 | 22,517.90 | |
| Sub | S/c Testing charges | 4,503.58 | 1.000 | 10.00 | 10.00 | 45,035.80 | |
| Sub | S/c Curing & other Miscellaneous Works | 4,503.58 | 1.018 | 10.00 | 10.18 | 45,846.44 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 4,503.58 | 25.000 | 15.00 | 375.00 | 1,688,842.50 | |
| P&M | Pumping & Lifting Charges | 4,503.58 | 1.000 | 614.82 | 614.82 | 2,768,891.06 | |
| 4,503.58 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹6,883.00 | ₹30,998,141.14 | |||||