Item Analysis

Sale Value

₹45,585,237

Budget Value

₹30,998,141

Mat

₹24,828,237

Sub

₹90,882

FW

₹0

P&M

₹2,768,891

PRW

₹3,310,131

Variance

₹0

Activity Name

CS.13.5.C - M45 RCC

BOQ Quantity

4,503.58 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M45 GRADE (INTERNAL) 4,503.58 1.000 5,513.00 5,513.00 24,828,236.54
PRW L/c for pouring of RCC Concrete 4,503.58 1.000 345.00 345.00 1,553,735.10
PRW L/c Curing of concrete 4,503.58 1.000 10.00 10.00 45,035.80
PRW L/C for Hacking 4,503.58 10.000 0.50 5.00 22,517.90
Sub S/c Testing charges 4,503.58 1.000 10.00 10.00 45,035.80
Sub S/c Curing & other Miscellaneous Works 4,503.58 1.018 10.00 10.18 45,846.44
PRW L/c for Lifting of concrete - PCC/RCC 4,503.58 25.000 15.00 375.00 1,688,842.50
P&M Pumping & Lifting Charges 4,503.58 1.000 614.82 614.82 2,768,891.06
4,503.58 0.000 0.00 0.00 0.00
Selected Item Totals: ₹6,883.00 ₹30,998,141.14