Item Analysis

Sale Value

₹26,739,598

Budget Value

₹18,182,040

Mat

₹14,385,455

Sub

₹55,923

FW

₹0

P&M

₹1,703,808

PRW

₹2,036,854

Variance

₹0

Activity Name

CS.13.5.B - M45 RCC

BOQ Quantity

2,771.23 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M45 GRADE 2,771.23 1.000 5,191.00 5,191.00 14,385,454.93
PRW L/c for pouring of RCC Concrete 2,771.23 1.000 345.00 345.00 956,074.35
PRW L/c Curing of concrete 2,771.23 1.000 10.00 10.00 27,712.30
PRW L/C for Hacking 2,771.23 10.000 0.50 5.00 13,856.15
Sub S/c Testing charges 2,771.23 1.000 10.00 10.00 27,712.30
Sub S/c Curing & other Miscellaneous Works 2,771.23 1.018 10.00 10.18 28,211.12
PRW L/c for Lifting of concrete - PCC/RCC 2,771.23 25.000 15.00 375.00 1,039,211.25
P&M Pumping & Lifting Charges 2,771.23 1.000 614.82 614.82 1,703,807.63
2,771.23 0.000 0.00 0.00 0.00
Selected Item Totals: ₹6,561.00 ₹18,182,040.03