Activity Name
CS.13.4.A - M20 RCC
BOQ Quantity
9.00 Cum
| Type | Description | Scope Qty | Coeff. | Rate | Unit Rate | Total (₹) | Actions |
|---|---|---|---|---|---|---|---|
| Mat | READY MIX CONCRETE-M20 GRADE | 9.00 | 1.000 | 4,280.00 | 4,280.00 | 38,520.00 | |
| PRW | L/c for pouring of RCC Concrete | 9.00 | 1.000 | 345.00 | 345.00 | 3,105.00 | |
| PRW | L/c Curing of concrete | 9.00 | 1.000 | 10.00 | 10.00 | 90.00 | |
| PRW | L/C for Hacking | 9.00 | 10.000 | 0.50 | 5.00 | 45.00 | |
| Sub | S/c Testing charges | 9.00 | 1.000 | 10.00 | 10.00 | 90.00 | |
| Sub | S/c Curing & other Miscellaneous Works | 9.00 | 0.853 | 10.00 | 8.53 | 76.77 | |
| PRW | L/c for Lifting of concrete - PCC/RCC | 9.00 | 20.000 | 15.00 | 300.00 | 2,700.00 | |
| P&M | Pumping & Lifting Charges | 9.00 | 1.000 | 614.82 | 614.82 | 5,533.38 | |
| 9.00 | 0.000 | 0.00 | 0.00 | 0.00 | |||
| Selected Item Totals: | ₹5,573.35 | ₹50,160.15 | |||||