Item Analysis

Sale Value

₹25,615,741

Budget Value

₹17,418,044

Mat

₹14,270,370

Sub

₹55,476

FW

₹0

P&M

₹1,690,177

PRW

₹1,402,021

Variance

₹0

Activity Name

CS.13.2.B - M45 RCC

BOQ Quantity

2,749.06 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M45 GRADE 2,749.06 1.000 5,191.00 5,191.00 14,270,370.46
PRW L/c for pouring of RCC Concrete 2,749.06 1.000 345.00 345.00 948,425.70
PRW L/c Curing of concrete 2,749.06 1.000 10.00 10.00 27,490.60
PRW L/C for Hacking 2,749.06 10.000 0.50 5.00 13,745.30
Sub S/c Testing charges 2,749.06 1.000 10.00 10.00 27,490.60
Sub S/c Curing & other Miscellaneous Works 2,749.06 1.018 10.00 10.18 27,985.43
PRW L/c for Lifting of concrete - PCC/RCC 2,749.06 10.000 15.00 150.00 412,359.00
P&M Pumping & Lifting Charges 2,749.06 1.000 614.82 614.82 1,690,177.07
2,749.06 0.000 0.00 0.00 0.00
Selected Item Totals: ₹6,336.00 ₹17,418,044.16