Item Analysis

Sale Value

₹23,307,960

Budget Value

₹15,848,655

Mat

₹13,230,825

Sub

₹51,315

FW

₹0

P&M

₹1,503,063

PRW

₹1,063,453

Variance

₹0

Activity Name

CS.13.1.D - M50 RCC

BOQ Quantity

2,444.72 Cum

Type Description Scope Qty Coeff. Rate Unit Rate Total (₹) Actions
Mat READY MIX CONCRETE-M50 GRADE 2,444.72 1.000 5,412.00 5,412.00 13,230,824.64
PRW L/c for pouring of RCC Concrete 2,444.72 1.000 345.00 345.00 843,428.40
PRW L/c Curing of concrete 2,444.72 1.000 10.00 10.00 24,447.20
PRW L/C for Hacking 2,444.72 10.000 0.50 5.00 12,223.60
Sub S/c Testing charges 2,444.72 1.000 10.00 10.00 24,447.20
Sub S/c Curing & other Miscellaneous Works 2,444.72 1.099 10.00 10.99 26,867.47
PRW L/c for Lifting of concrete - PCC/RCC 2,444.72 5.000 15.00 75.00 183,354.00
P&M Pumping & Lifting Charges 2,444.72 1.000 614.82 614.82 1,503,062.75
2,444.72 0.000 0.00 0.00 0.00
Selected Item Totals: ₹6,482.81 ₹15,848,655.26